7         GEOLOGY AND HYDROGEOLOGY

7.1   Introduction And Methodology

This chapter examines and assesses the geological, geotechnical and hydrogeological impact of the route options on the study area.  Each of the route options are divided into sections. This allows them to be compared to adjacent sections of other routes.  Each of the route sections have been examined and the major constraints and construction features identified and assessed.

The assessment falls broadly into four categories:

Geotechnical: the lengths and heights/depths of embankments and cuttings, the presence of soft ground and depths of peat bog and marsh areas.  The presence of other features within the route sections are also considered.

Geological: the composition of the underlying geology particularly the depth to rock in cuttings and the composition and thickness of the overburden geology.

Material Balance: the cut/fill balance of the route sections, the volume of rock excavation and the volume of unsuitable material.

Hydrogeological: the presence and vulnerability of aquifers and groundwater users.

The assessment of the constraints and construction features allow each route section to be given an overall impact rating based on the effect it would have on the environment, the difficulty of the engineering solution and the resultant cost implications.

Each route section is discussed in detail later in this chapter and an impact assessment made.  In assessing the impacts the following significance criteria have been used:

Impact

Significance Criteria

Severe adverse impact

 

Deep cutting or high embankment for the majority of route.  Significant rock excavation.  Large quantity of other suitable/unsuitable material excavated.  Large quantity of material exported and imported.  Majority of route crosses peat or soft ground.

Permanent impact on major aquifer.  Significant impact on groundwater flow/quality.

Major adverse impact

 

Deep cutting or high embankment for significant sections of route.  Major rock excavation.  Major amount of other suitable/ unsuitable material to be excavated.  Major quantity of material exported and imported.  Major parts of route cross peat or soft ground.

Temporary impact on major aquifer.

Major impact on groundwater flow/quality.

Moderate adverse impact

 

Deep cuttings or high embankments at a number of locations along route.  Moderate excavation of rock.  Moderate amount of other suitable/ unsuitable material to be excavated.  Moderate quantity of material to be exported and imported.  Localised sections of route cross peat or soft ground.

Permanent effect on poor/minor which is locally productive. Moderate impact on groundwater flow/quality.

Minor adverse impact

 

Deep cuttings or high embankments at a few locations.  Rock excavations in localised areas.  Small amount of other suitable/ unsuitable material to be imported and exported.  Short sections of route cross peat or soft ground.  Temporary effect on poor/minor aquifer which is locally productive. Adverse Minor impact on groundwater flow/quality.

No impact

No significant effect

Minor beneficial impact

Creation of new sites of geological/geomorphological interest.  Improvement to local resources through introduction of pollution control or flow balancing measures. 

 

Sources of information for this assessment are:

·       N22 Ballyvourney – Macroom – Ballincollig Constraints Study Report, October 2001

·       Bedrock geology mapping for South Cork

·       Bedrock geology mapping for Kerry-Cork

·       Six-inch drift geology field maps

·       National Wells Database

·       GSI interim aquifer classification scheme

·       Vulnerability mapping

·       Karst database

·       Water Quality in Ireland 1995 – 1997 (EPA, 1999)

·       Shanakill Landfill location

·       Ballincollig Bypass Site Investigation Report

·       Aerial Photography

The geological mapping and well information was obtained from the Geological Survey of Ireland (GSI).  The Shanakill landfill location, the Ballincollig Bypass site investigation report and details of groundwater source locations were obtained from Cork County Council.

No site investigation has been undertaken as part of the route selection assessment.  Currently the Ballincollig Bypass and Macroom Bridge site investigation reports provide the only confirmed ground condition information for the study area.  A ground investigation will be undertaken on the preferred route once it has been confirmed.

7.2   Existing Environment

7.2.1 Solid Geology

The bedrock geology mapping has been compiled from the ‘Geology of South Cork’ and the ‘Geology of Kerry-Cork’.

The study area is underlain by Devonian Old Red Sandstone and Carboniferous Limestone.  The Old Red Sandstone and Limestone comprise various geological units or formations.  These are given for reference in Table 7.1 below.

Table 7.1: Geological Units Found Within Study Area

Geological Unit

Description

O

L

D

 

R

E

D

 

S

A

N

D

S

T

O

N

E

Bird Hill Formation (BH)

Purple siltstone and fine grained sandstone

Ballytrasna Formation (BS)

 

Purple mudstone and pale red fine to medium grained sandstone

Castlehaven Formation (CE)

 

Purple mudstones and siltstones with interbedded sandstone units

Caha Mountain Formation (CH)

Purple and green sandstone and siltstone

Gortanimill Formation (GM)

Green fine grained sandstone and siltstone

Gun Point Formation (GM)

Purple and green medium and coarse grained sandstones with thin interbedded purple siltstones

Gyleen Formation (GY)

 

Green to grey and purple mudstones and sandstones

Kinsale Formation (KNcu)

Flaser-bedded sandstone and mudstone

Old Head Sandstone Formation (OH)

 

Grey sandstones and heterolithic bedded sandstones and mudstones

Toe Head Formation (TH)

Cross bedded sandstones with minor mudstones

L

I

M

E

S

T

O

N

E

Ballysteen Formation (BA)

 

 

Dark grey well-bedded fossiliferous muddy limestone

Little Island Formation (LI)

 

 

Massive and crinoidal limestone and wackestone

Waulsortian Limestones (WA)

Massive calcareous mudstones, wackestones and packstones

 

The various formations of the Old Red Sandstone underlie much of the study area outcropping as the Southern Derrynasaggart Mountain succession west of Macroom and the Central Cork succession to the east.

Interspersing the Old Red Sandstone within the study area are two limestone outcrops.  These are associated with two synclines; the Macroom – Blarney Syncline to the north and the Cork Syncline to the south.

The Macroom – Blarney Syncline trends east-northeast to west-southwest across the study area underlying Coachford and terminating at the floodplain area of the River Lee south of Macroom.  Rock type varies along the syncline with Waulsortian Limestones underlying the floodplain area and the Gyleen and Kinsale formations of the Old Red Sandstone forming the syncline further to the east.

The Cork Syncline also plunges east-northeast to west-southwest through the eastern end of the study area underlying Ovens and Crookstown.  The Ballysteen and Little Island formations and the Waulsortian Limestones are present along the syncline.  Solution features may be associated with the Waulsortian Limestone which is classified as karstic on the Groundwater Protection Scheme map produced by the GSI. Generally the low lying ground within the study area is underlain by limestone with the remainder of the area and higher ground underlain by the Old Red Sandstone.

7.2.2 Overburden Geology

The overburden or drift geology information within the study area has been obtained from six-inch field maps for County Cork (circa 1850), aerial photographs and a visual inspection of the study area. No quaternary mapping is available for the study area and there is very little information as to the depth of overburden.

The drift deposits across the study area are mainly glacial in origin consisting of sandy gravel with many cobbles, boulders and larger particles.  Alluvial deposits are also present along and adjacent to the rivers that pass through the study area.  These deposits are likely to consist of soft compressible clay, silts, sands and gravels.  Localised bogs and marshes are recorded on the six-inch field maps in low lying areas adjacent to many of the rivers and some areas of poorly drained high ground west of Macroom.

The depths of the drift deposits within the study area are related to the topography.  The areas of high ground and steep slopes, which cover much of the study area, consist predominantly of rock outcrops at or close to the surface, with generally very little overburden.  The depth of overburden tends to increase as the elevation of the ground decreases and the gentler slopes to the hills of the lower areas indicate a greater thickness of drift deposit.  The greatest thickness of overburden is in the low lying areas, generally coinciding with areas underlain by limestone. The majority of the study area west of Macroom consists of rock outcrops and shallow overburden.  Whilst the area to the east has the greatest depths of overburden.

7.2.3 Contaminated Land

Shanakill landfill is situated approximately 3 km north-east of Macroom near the River Laney. The facility closed in 1996 but when operating accepted approximately 4500 tonnes of municipal and inert waste per annum.

The landfill covers an area of approximately 0.35 hectares (3500 m2), however, it should be considered that potentially a much larger area could be affected by leachate and/or landfill gas. 

From the information available Shanakill landfill appears to be the only area of contaminated land within the study area.

7.2.4 Hydrogeology

Aquifer details were obtained from the Geological Survey of Ireland (GSI) who have an interim aquifer classification scheme. This indicates generally unproductive zones in the west, moderately productive zones in the east and west, and areas of good development potential and fissure flow associated with limestone bedrock.  The more productive zones are a greater constraint to potential development.  A plan showing the location of the zones is included in the Constraints Study Report.

A review of the “Major Aquifers of Ireland” (1982) map shows areas of Minor/Complex Sand and Gravel aquifers which appeared to be associated with the Sullane River between Ballyvourney and Chransaigh and the Bride River between Crookstown and Ovens.

Vulnerability mapping is used to identify the likelihood of contamination reaching an aquifer as a result of contamination at or near the surface.  This depends upon the type and thickness of soils and upon the presence of karst or other highly permeable features.  GSI have interim vulnerability mapping for the area, based on outcrops recorded on field sheets, which adopts a classification of extreme vulnerability where there are outcrops and high to low vulnerability elsewhere.  Areas of extreme vulnerability occur frequently across the Study Area, as there is generally less than 5m of overburden.

The presence of karst can increase vulnerability through rapid movement of water.  The GSI karst database was examined for karst features.  Two were identified; Coleman Cave at Barnagore and a swallow hole at Ballygroman.  These are in areas of Waulsortian limestone where there is a likelihood of karst occurrence.

Information on groundwater quality was obtained from Water Quality in Ireland (1995-1997.EPA 1999).  The data was limited but indicated quality to be good and to meet drinking water standards (see Table 4.2.1 in the Constraint Report).  It is likely that many domestic well supplies are untreated.  Groundwater wells installed in areas where rock outcrop is shallow (e.g. < 2m to surface) are likely to be susceptible to pollution. 

7.3   Assessment Of Effects: Construction And Operation

7.3.1 Geotechnical

The depth to bedrock varies across the study area.  West of Macroom the rock is generally close to the ground surface and there are frequent rock outcrops interspersing areas of shallow overburden. It is likely, therefore, that rock will be encountered in most cuttings between Ballyvourney and Macroom and be absent only in the shallowest cuttings.  It is also likely that rock will be the founding strata for any structures in this section.  East of Macroom there is generally a greater depth of material overlying the bedrock and although dependent on location the depth to rock in cuttings will therefore also be greater.

Where rock is exposed it should, after removal of weathered or loose material, prove to be an adequate construction material either in cuttings or as a founding strata for structures.  Given the proximity of rock to the ground surface west of Macroom it is probable that there will be a greater depth of weathered material present and removal of rock in these areas should be possible by mechanical means.  Generally throughout the route however, where there are long or deep cuttings, the volume of material to be removed makes blasting a more economical option.

The majority of rock encountered will consist of various formations of the Old Red Sandstone, however limestone may be encountered in the Bride Valley area between Crookstown and Ovens.  Solution features may be present in the limestone, the depth below ground of which varies across the valley.  Should a route be chosen that crosses this area detailed ground investigation will be needed to negate the possibility of cavities beneath the proposed construction.

The glacial and alluvial deposits overlying the solid strata will generally be suitable for use in the new road construction as a fill or foundation material for embankments.  The glacial deposits should also be suitable as a founding stratum for structural foundations.

A reservoir crossing is required on each of the route options.  The length of crossing will vary depending on the route chosen but it is probable that piled foundations passing through the glacial and alluvial deposits and anchoring in intact bedrock will be required for this structure.

Localised areas of soft ground, bog and marsh exist throughout the study area.  West of Macroom these soft ground areas may be associated with poor drainage due to the shallow depth of the underlying bedrock and are therefore likely to be of limited depth.

Although no confirmation of the depths of the soft deposits are available at this time, it is likely that the greatest thickness will occur in the Bride Valley where there is an extensive bog area.  It is envisaged that soft deposits, where encountered, will be removed and replaced with a suitable fill material.  However, depending on the volume of material involved, alternate forms of ground treatment, including leaving the soft ground in-situ, may become more economical options.

7.3.2 Groundwater

Potential impacts on groundwater during the construction phase include pollution through contaminated run-off or spillage; alteration of the groundwater flow regime by construction of cut-offs, de-watering or groundwater abstraction for construction purposes; impact on groundwater users and impact on ecology (for example where river baseflow or wetlands depend on groundwater). 

During operation the potential impacts are pollution; permanent alteration of the flow regime where cuttings or cut-off walls intercept groundwater flow; and effects on groundwater users and ecology through lowering of the water table.

The following assessment concentrates mainly on aquifer status.  To avoid the risk of pollution of and impacts on aquifers, the preferred route (hydrogeologically), would cross less productive and less vulnerable aquifers.

There are other issues such as disposal of road drainage, impacts on wetlands and river base flow, and impacts on domestic water supply from wells.  Each of these is assessed either directly or indirectly in other sections as follows:

Surface Water: Road drainage.  The majority of the routes cross or pass near to rivers, therefore it is probable that road drainage would be designed to discharge principally to surface water rather than groundwater.  Sections where the proposed routes do not cross rivers include: Yellow route nodes 1 to 2, Yellow route nodes 6 to 7, and Link between nodes 12 and 12a.

Ecology: Impacts on wetlands and river base flows.  Ecological features are identified in the ecology section so are not included again in the hydrogeological assessment.  Some features may be dependent on groundwater.

Water supply: Information was obtained from the National Wells Database and well locations were provided with varying degrees of accuracy.  This data was not sufficiently accurate to define the number and depth of supply wells that may be affected by the proposed routes.  Further investigation will be undertaken at preliminary design stage to ascertain possible affects and mitigation measures.

 

7.4   Mitigation Proposals

There are two main mitigation measures that could be used to reduce the geotechnical impact of the construction of the road.

1. Minimise the heights of embankments and depths of cuttings along the route.

Minimising the heights and depths of these features would reduce their visual impact on surrounding areas and reduce the landtake required for them. Minimising the heights of the embankments would also reduce the volume of fill material required along the route.

Reducing the depths of cuttings would reduce the amount of rock requiring removal and reduce the effect of the cutting on the surrounding groundwater regime.

2. Use a balanced cut and fill design over the length of the route.

By having a balanced cut and fill design the requirement for importing additional or removing excess material would be negated representing a cost saving to the overall scheme and reducing the overall environmental impact of the road.

The criterion for a balanced cut and fill design should be applied to individual logical sections rather than the complete route as a whole. This will ensure that transport of materials remains localised within these sections as opposed to the possibility of having to be hauled over long distances in order to achieve a good cut and fill balance, a situation which would be undesirable and uneconomical. 

Contaminated Ground

There are measures that can be taken to reduce the impact of road construction adjacent to the closed landfill.  These include a suitably detailed ground investigation in the area to determine the extents of the landfill, the installation of monitoring boreholes and a gas-monitoring regime to determine whether landfill gas is present at the location of the proposed road construction.  Depending on the results of the site investigation and monitoring a suitable earthworks design would be produced incorporating measures to deal with contaminated land and/or landfill gas.

Hydrogeology

To reduce the impact on aquifers the amount of soil removed from the site would be minimised so that the thickness of protective soils is retained where possible and aquifer vulnerability is not increased.  To minimise the effects of cuts on the groundwater regime they would be kept to a minimum depth.  The potential impact of road drainage on groundwater quality would be minimised by adopting drainage and pollution control measures.  These could include positive drainage measures such as oil interceptors, silt traps and spillage containment.

 

7.5   Assessment Of Routes

Definitions of the classifications of height of cuttings and depths of embankments used in the route assessments are given below:

Classification

Height/Depth Description

Low Embankment

Less than 2 m high

Medium Embankment

2 m to 10 m high

High Embankment

Greater than 10 m high

Shallow Cutting

Less than 2 m deep

Medium Cutting

2 m to 10 m deep

Deep Cutting

Greater than 10 m deep

 

7.5.1 Node Assessment

Node 1 To 3

Two route options exist between nodes 1 and 3:

Green Route Section G/01 & G/02

Moderate Adverse Geological Impact.  This route comprises mainly low and medium embankment and low cutting. There is a short length of high embankment (maximum height 12 m) and some medium depth cutting (up to 9 m deep). There are no peat or soft ground areas. The shallow depth of overburden in this area means that the majority of cutting is in rock. There is a moderate excess of fill with rock comprising the majority of the excavated material.

 

Minor Adverse Hydrogeological Impact.  The aquifer is defined as moderately productive locally.

Yellow Route Section Y/01 & Y/02

Moderate Adverse Geological Impact.  This route comprises mainly low and medium embankment and medium cutting with a short length at grade. There are no high embankments or deep cuttings (maximum embankment height is 9.5 m and maximum depth of cutting is 8 m). There are no peat or soft ground areas. The majority of cutting is in rock and this route has a good material balance.

Minor Adverse Hydrogeological Impact.  The aquifer is defined as moderately productive locally.

Node 3 to 6/7

One route option exists between nodes 3 and 6:

Green Route Sections G/03, G/04 & G/04a

Major Adverse Geological Impact.  The majority of this route is on low and medium embankment with a short length of high embankment (up to 12.5 m height). Maximum depth of cutting is 22 m.  The majority of cutting is in rock and almost three-quarters of excavated material comprises rock.  There is a moderate length of peat along the route, mainly present under embankment.  It is anticipated that the depth of peat would be fairly shallow. Primarily the depth of cutting raises this route to a major adverse impact on the area although the presence of the peat deposits contributes to this assessment.

Minor Adverse Hydrogeological Impact.  Aquifer is moderately productive locally to the west and generally unproductive to the east.

Node 3 to 7a

Two route options exist between nodes 3 and 7a:

Yellow Route Sections Y/03 to Y/06a

Major Adverse Geological Impact.  The majority of this route is on low and medium embankment with a short length of high embankment (maximum height 21 m).  Maximum depth of cutting along the route is 14 m with approximately one-third of cutting in rock.  A short length of peat is present along the route, mainly under embankment.

Minor Adverse Hydrogeological Impact.  Aquifer is moderately productive locally to the west and generally unproductive to the east.

Green/Yellow Route Combination Sections G/03,  L/01 and Y/05 to Y/06a

Major Adverse Geological Impact.  This route comprises mainly low and medium embankment with a short length of high embankment (maximum height 21 m).  Maximum depth of cutting along the route is 22 m.  The majority of cutting is in hard strata with approximately two-thirds of excavated material comprising rock.  There is a moderate length of peat present along the route, nearly all under embankment.  It is anticipated that the depth of these soft deposits would be fairly shallow.  The high embankments and deep cuttings give this route a major adverse impact on the surrounding area.  The peat deposits are also a contributory factor to this assessment.

Minor Adverse Hydrogeological Impact.  Aquifer is moderately productive locally to the west and generally unproductive to the east.

Node 6 to 14

Two route options exist between nodes 6 and 14:

Green Route Sections G/05 and G/06

Moderate Adverse Geological Impact.  The majority of the route is in shallow and medium cutting.  There are no deep cuttings.  Maximum embankment height along the route is 15 m. Approximately one-third of cutting is in rock and there is a short length of peat along the route.  The route passes within one hundred and twenty metres of a closed landfill in section G/05 which poses a constraint to any development, including road construction, within its vicinity.  Mitigation measures, however, will reduce the impact of any problems associated with the landfill.

Minor Adverse Hydrogeological Impact.  The route between nodes 6 and 14 is generally moderately productive aquifer with some locally productive areas.

Green/Red Route Combination Sections G/05, L/03 and R/03

Major Adverse Geological Impact.  The majority of the route is on medium embankment or in medium cutting.  There is a short length of high embankment (maximum height 23.5m).  There is no deep cutting along the route.  Approximately one-third of cutting is in rock.  There are no peat areas along the route.  This route shares section G/05 of the Green route and therefore also passes close to the closed landfill. The route generally has a moderate adverse impact, however, the maximum embankment height increases the assessment to major adverse impact.

Minor Adverse Hydrogeological Impact.  The route between nodes 6 and 14 is generally moderately productive aquifer with some locally productive areas.

Node 7 to 14

One route option exists between nodes 7 and 14:

Red Route Sections R/01 to R/03

Major Adverse Geological Impact.  The majority of the route is on medium embankment or in medium cutting.  There is a short length of high embankment (maximum height 23.5m).  There is no deep cutting along the route.  Approximately one-third of cutting is in hard strata and over half the excavated material comprises rock.  There are no peat areas along the route.  If the embankment heights in this section could be reduced the impact assessment would improve.

Minor Adverse Hydrogeological Impact.  The route between nodes 6 and 14 is generally moderately productive aquifer with some locally productive areas.

Node 7a to 11

Two route options exist between nodes 7a and 11:

Yellow Route Sections Y/07 and Y/08

Major Adverse Geological Impact.  The majority of the route is on medium embankment or in medium cutting.  There is a short length of high embankment (maximum height 15 m) and a short length of deep cutting (maximum depth 25m).  Approximately half the length of cutting is in rock.  There is a negligible length of peat along the route.  There is also an imbalance in cut and fill which contributes to the impact assessment of this section.

Minor Adverse Hydrogeological Impact.  The aquifer is generally unproductive in the northern part; crosses the limestone aquifer to the south of Macroom and is then generally moderately productive.

Yellow/Blue Route Combination Sections Y/07, L/04 and B/02

Major Adverse Geological Impact.  The majority of the route is on low and medium embankment.  There is no high embankment.  There is a short length of deep cutting (maximum depth 17 m).  Half the length of cutting is in rock.  There is a negligible length of peat along the route.  There is a small deficit of fill material for this route which contributes to the impact assessment.  If cutting depths and/or the fill deficit were reduced the impact assessment of this section would improve.

Minor Adverse Hydrogeological Impact.  The aquifer is generally unproductive in the northern part; crosses the limestone aquifer to the south of Macroom and is then generally moderately productive.

Node 7b to 11

One route option exists between node 7b and 11:

Blue Route Sections B/01 and B/02

Moderate Adverse Geological Impact.  The majority of the route is on low and medium embankment.  There is a short length of high embankment (maximum height 13 m) and a short length of deep cutting (maximum depth 14.5 m).  Two-thirds of the length of cutting is in rock.  There are no peat or soft ground areas present along the route.  Although this route contains sections of high embankment and deep cutting, the heights/depths and lengths of these features do not greatly exacerbate the impact of this section.

Minor Adverse Hydrogeological Impact.  The aquifer is generally unproductive in the north and moderately productive in the south.

Node 11 to 15

Three route options exist between node 11 and 15:

Yellow Route Sections Y/09 and Y/10

Moderate to Major Adverse Geological Impact.  The majority of the route is on low and medium embankment (maximum height 8 m - this is a localised area of fill to an existing quarry, finished level proposed to approximately 1m above the surrounding ground level).  There is no high embankment or deep cutting along the route (maximum depth of cutting 4.5 m).  A short length of peat or soft ground is present along the route.  The depth of soft deposits may be several metres but it is envisaged that these will be removed and replaced with a suitable fill rather than a more elaborate form of ground treatment being required.  This section has a significant fill material deficit.

Moderate Adverse Hydrogeological Impact.  The proposed route crosses a moderately productive aquifer to the west and limestone aquifer to the east.

Blue Route Sections B/03 and B/04

Major Adverse Geological Impact.  The majority of the route is on low embankment.  There is no high embankment or deep cutting along the route; maximum height of embankment is 4.5 m and maximum depth of cutting is 3 m.  There is a moderate amount of peat along this route, almost one-sixth of the length of the route being in or over soft ground.  The soft deposits may be of such depth that their removal and replacement may be an uneconomical solution and an alternative form of ground treatment required.

Major Adverse Hydrogeological Impact.  Almost the entire section crosses the limestone aquifer with potential for karst and fissure flow.

Yellow/Blue Route Combination Sections Y/09, L/06 and B/04

Major Adverse Geological Impact.  The majority of the route is on low and medium embankment.  There is no high embankment or deep cutting along the route.  One-fifth of the route is at grade.  A short length of peat is present along the route.  A deficit of fill material is the major contributor to the impact assessment, which could be improved if the deficit were to be reduced.

Moderate Adverse Hydrogeological Impact.  The proposed route crosses a moderately productive aquifer to the west and limestone aquifer to the east.

 

7.6   Conclusions

The preferred route hydrogeologically is Green linked to Yellow then Red.

Between nodes 1 and 3 the Yellow route is the preferred option.  The main advantages of this option are the absence of any high embankments, a short length of which is present on the Green route.  The Yellow route also has a very good overall cut and fill balance compared with the Green route, which has a large material surplus.

Between nodes 3 and 6/7a there are three route options; Green, Yellow and Green/Link1/ Yellow. All three of these options are assessed as having major adverse impacts.  Comparatively, however, the least favourable option is the Green/Link1/Yellow route which incorporates the worst features of both the alternatives by having the greatest length of high embankment and deep cutting. This route also crosses the greatest length of soft ground.  The preferred option for this section is the Yellow route which has shallower cuttings, crosses less soft ground and has a better cut and fill balance than the Green route. The only disadvantage of this route is that it has more high embankment compared to the Green route and maximum embankment height is also greater.

East of Macroom there are the northern (Green and Red) routes and the southern (Yellow and Blue) routes.  For the northern routes between nodes 6/7 and 14 there are three possible options; Green, Red and Green/Link3/Red.  The preferred route option for this section is the Green route due to its shorter length of high embankment and the 15 m maximum height of the embankment.  Although this route passes close to the closed landfill at Shanakill this does not dominate the impact rating.  Mitigation measures should ensure that construction near the landfill would cause few problems.  The Red and Green/Link3/Red route options were less preferred because of the 23.5 m maximum embankment height and longer lengths of high embankment.

For the southern routes between nodes 7a/7b and 11 there are three route options; Yellow, Blue and Yellow/Link4/Blue.  The Blue route is the preferred option because of its superior cut and fill balance and the absence of any soft ground.  The Yellow/Link4/Blue route option is slightly less favourable due to a short length of soft ground and a cut and fill balance resulting in a slight deficit of material.  The Yellow route is the least preferred option because of the presence of a length of very high embankment and a cut and fill balance resulting in a large fill material surplus.

For the southern routes between nodes 11 and 15 the Blue route is the least preferred option due to the length of soft ground encountered but it has the best cut and fill balance.  Conversely the Yellow and Yellow/Link6/Blue route options are both equally preferable except for poor cut and fill balances resulting in a substantial deficit of fill material.  In this situation the cut and fill balance of the routes is the more important engineering problem to be solved and so takes precedent over the length of soft ground likely to be encountered therefore the Blue route is the preferred option.

East of Macroom the overall preferred route is the Green (northern) route.  Although the Green (northern) and Blue (southern) routes have similar impact assessments the advantages of this route are that it doesn’t have any lengths of deep cutting and it crosses a shorter length of soft ground.   

Embankment and cutting slopes of 1 vertical to 2 horizontal (1V:2H) have nominally been assumed for the route options.  For the preferred route it is likely that there will be some deviation from this assumption particularly in rock cuttings.  Where the cutting is in intact rock, slopes considerably steeper than 1V:2H can be used.  For cuttings where the rock is overlain by a depth of overburden, two-part slopes will most likely be used with the upper (soil) part of the slope at 1V:2H and the lower (rock) part at a steeper angle.

The majority of embankments will have side slopes of 1V:2H, however, for high embankments or embankments over soft ground shallower slopes will be required.

 

Back to Contents