18    CONSTRUCTION COST ESTIMATE

18.1  Introduction

This Chapter outlines the method and unit price that were used to derive the cost estimate for the route options.  The unit rates used to derive the cost estimate are based on prices obtained in the first quarter of 2001 (Q1/01).

18.2  Cost Estimate Rates

Cost Estimates were prepared for each route option using the headings detailed below. These series numbers correspond to the NRA Manual of Contract Documents for Road Works, with the exception of Series 2600, 2700, 5000 and 6000. These Series have been used as classifications of some items not identified with series numbers in the NRA Manual of Contract Documents for Road Works.

·       Series 200 Site Clearance

·       Series 300 Fences

·       Series 400 Safety Barriers and Pedestrian Guardrails

·       Series 500 Drainage and Service Ducts

·       Series 600 Earthworks

·       Series 900 Road Pavements – Bituminous Bound Materials

·       Series 1100      Kerbs, Footways and Paved Areas

·       Series 1200      Traffic Signs

·       Series 1300      Road Lighting Columns and Brackets

·       Series 1400      Electrical Work for Road Lighting and Traffic Signs

·       Series 1700      Structural Concrete

·       Series 2600      Junctions and Intersections

·       Series 2700      Accommodation Works/Statutory Undertaker’s Diversions

·       Series 5000      Land Acquisition

·       Series 6000      Contingencies

All quantities have been measured from the design, with the exception of Series 1200, 1300, 1400, 2700 and 6000. Series 1200, 1300 and 1400 are calculated as 2%, 1% and 1%, respectively, of the total construction cost excluding land and structures. Series 2700 contains items 2700/01, 2700/02 and 2700/04, Accommodation Works, Statutory Undertaker’s Diversion and Preliminaries respectively. These are calculated as 3%, 5% and 15% respectively, items 2700/01 and 2700/02 based on the total construction cost excluding land and structures, and item 2700/04 being based on the total construction cost excluding land. Series 6000 is calculated at 10% of the total cost.

18.3  Scheme Cost Estimates

The Cost Estimates for each nodal section of the proposed route options are shown below:

 

 

Node

Length
(m)

Construction
cost

10% contingency
& uplift on
tender

Land cost

Design & supervision
(8% & 5%)

VAT
(@ 12.5%)

Total
(ex. VAT)

 

 

From

To

Amounts shown are in Thousands of Euro (€ / 1000)

West of Macroom

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Green

 

1

2

1,506

4,138

414

432

592

569

5,575

 

 

2

3

518

1,869

187

130

267

257

2,453

 

 

3

4

6,578

19,943

1,994

2,293

2,852

2,742

27,082

 

 

4

5

5,363

11,372

1,137

1,860

1,626

1,564

15,995

 

 

5

5a

1,582

4,182

418

203

598

575

5,401

 

 

5a

6

1,646

9,671

967

356

1,383

1,330

12,377

 

Additional Length for Macroom Bypass

ex. N22

5

N/A

5,101

510

479

729

701

6,819

 

 

 

 

17,193

56,275

5,627

5,752

8,047

7,738

75,702

 

 

 

 

 

 

 

 

 

 

 

Yellow

Additional Length for N22 tie-in

ex. N22

1

700

1,270

254

76

198

190

1,798

 

 

1

2

589

5,103

510

216

730

702

6,559

 

 

2

3

516

970

97

65

139

133

1,271

 

 

3

3a

3,762

9,975

998

761

1,426

1,372

13,160

 

 

3a

5

8,652

18,891

1,889

1,775

2,701

2,598

25,257

 

 

5

5a

1,582

4,182

418

203

598

575

5,401

 

 

5a

6

1,646

9,671

967

356

1,383

1,330

12,377

 

 

 

 

17,447

50,062

5,133

3,451

7,175

6,899

65,822

 

 

 

 

 

 

 

 

 

 

 

East of Macroom

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Green

 

6

9

6,047

13,112

1,311

2,635

1,875

1,803

18,933

(WS)

 

9

14

16,108

71,530

7,153

6,891

10,229

9,835

95,803

 

 

14

16

2,095

6,676

668

1,354

955

918

9,652

 

Additional Length for Macroom Bypass

6

7

1,947

8,401

840

356

1,201

1,155

10,798

 

Additional Length for Macroom Bypass

7

7a

928

4,511

451

178

645

620

5,785

 

 

 

 

27,125

104,230

10,423

11,412

14,905

14,332

140,971

 

 

 

 

 

 

 

 

 

 

 

Red

 

6

7

1,947

8,401

840

356

1,201

1,155

10,798

(WS)

 

7

7b

954

3,759

376

1,003

537

517

5,675

 

 

7b

13

9,504

47,079

4,708

3,714

6,732

6,473

62,234

 

 

13

14

9,151

26,133

2,613

4,411

3,737

3,593

36,894

 

 

14

16

2,095

6,676

668

1,354

955

918

9,652

 

Additional Length for Macroom Bypass

7

7a

928

4,511

451

178

645

620

5,785

 

 

 

 

24,579

96,559

9,656

11,015

13,808

13,277

131,037

 

 

 

 

 

 

 

 

 

 

 

Yellow

 

6

7

1,947

8,401

840

356

1,201

1,155

10,798

(DC)

 

7

7a

928

4,511

451

178

645

620

5,785

 

 

7a

8

5,260

40,875

4,088

1,606

5,845

5,620

52,414

 

 

8

11

5,211

22,667

2,267

1,835

3,241

3,117

30,010

 

 

11

12

9,087

32,227

3,223

2,082

4,608

4,431

42,141

 

 

12

15

4,284

17,151

1,715

2,021

2,453

2,358

23,340

 

 

15

16

333

666

67

61

95

92

888

 

 

 

 

27,050

126,498

12,650

8,139

18,089

17,393

165,376

 

 

 

 

 

 

 

 

 

 

 

Yellow

 

6

7

1,947

8,401

840

356

1,201

1,155

10,798

(WS)

 

7

7a

928

4,511

451

178

645

620

5,785

 

 

7a

8

5,260

37,149

3,715

1,606

5,312

5,108

47,782

 

 

8

11

5,211

18,913

1,891

1,835

2,705

2,600

25,343

 

 

11

12

9,087

26,331

2,633

2,082

3,765

3,621

34,812

 

 

12

15

4,284

14,351

1,435

2,021

2,052

1,973

19,859

 

 

15

16

333

455

45

61

65

63

626

 

 

 

 

27,050

110,109

11,011

8,139

15,746

15,140

145,005

 

 

 

 

 

 

 

 

 

 

 

Blue

 

6

7

1,947

8,401

840

356

1,201

1,155

10,798

(DC)

 

7

7b

954

3,759

376

1,003

537

517

5,675

 

 

7b

10

8,049

52,886

5,289

4,057

7,563

7,272

69,794

 

 

10

11

1,261

7,315

732

381

1,046

1,006

9,474

 

 

11

12a

10,622

43,271

4,327

4,203

6,188

5,950

57,989

 

 

12a

15

2,967

10,574

1,057

965

1,512

1,454

14,108

 

 

15

16

333

666

67

61

95

92

888

 

Additional Length for
Macroom Bypass

7

7a

928

4,511

451

178

645

620

5,785

 

 

 

 

27,061

131,382

13,138

11,203

18,788

18,065

174,510

 

 

 

 

 

 

 

 

 

 

 

Blue

 

6

7

1,947

8,401

840

356

1,201

1,155

10,798

(WS)

 

7

7b

954

3,759

376

1,003

537

517

5,675

 

 

7b

10

8,049

47,453

4,745

4,057

6,786

6,525

63,041

 

 

10

11

1,261

6,443

644

381

921

886

8,389

 

 

11

12a

10,622

36,352

3,635

4,203

5,198

4,998

49,388

 

 

12a

15

2,967

8,676

868

965

1,241

1,193

11,749

 

 

15

16

437

455

45

61

65

63

626

 

Additional Length for Macroom Bypass

7

7a

928

4,511

451

178

645

620

5,785

 

 

 

 

27,165

116,048

11,605

11,203

16,595

15,957

155,451

 

Note:  In the above cost estimate summary table, “Additional Length for Macroom Bypass” refers to the following:

West of Macroom:     In order to ensure that a viable, working bypass of Macrrom could be constructed as the first phase of the scheme, an additional length of road is required for the Green/Link/Yellow route option between Node 5a and the existing N22 near Carrigaphooca.  Further detail of this particular phasing requirement, which was requested by the NRA at a stage after the routes had been developed and investigated with regard to environmental impact, is covered in Chapter 17 of this report.  The cost of the “extra” section of road was established on a pro-rata basis of the section of the Yellow route between Nodes 3a and 5.

East of Macroom:      As a result of the same requirement to provide the Macroom Bypass as the first phase of the scheme, east of Macroom the Green route has the additional cost of the Macroom Bypass between Nodes 6 and 7a and the Blue and the Red routes between Nodes 7 and 7a.

 

For this scheme, it has been assumed that preparation (design) and supervision costs are 13.8% and 5% respectively of the total as used in the economic analysis section.  The table below shows the cost estimates for routes to the west and east of Macroom:

Total Scheme Costs

 

 

 

 

 

 

Amounts shown are in Thousands of Euro (€ / 1000)

West

East

Total

 

West

East

Total

Green/Link1/Yellow

75,702

Green (WS)

140,971

216,673

 

Yellow

65,822

Green (WS)

140,971

206,793

 

 

Red (WS)

131,037

206,739

 

 

 

Red (WS)

131,037

196,859

 

 

Yellow (DC)

165,376

241,078

 

 

 

Yellow (DC)

165,376

231,198

 

 

Yellow (WS)

145,005

220,707

 

 

 

Yellow (WS)

145,005

210,827

 

 

Blue (DC)

174,510

250,212

 

 

 

Blue (DC)

174,510

240,332

 

 

Blue (WS)

155,451

231,153

 

 

 

Blue (WS)

155,451

221,273

 

For scheme costs, it can be noted that the cheapest route would be construction of the Yellow Route to the west of Macroom and the Red route to the east.  However, it should be noted that the cheapest route may not be the most cost effective in terms that, for the cost, it may not pick up sufficient traffic to be value for money - see Chapter 19: Traffic and Economics.

 

Back to Contents