Traffic counts are carried out on an annual basis along the study section
of the N22 on behalf of the National Roads Authority. Data has been obtained
from the five regular count stations located between Ballyvourney and
Ballincollig, for the period 1987-2000.
This is not a complete dataset as only one site near the new cemetery at
Macroom, has produced data for each year between 1987 and 2000. Counts are usually carried out in September
and adjusted for monthly variations to give an estimate of Annual Average Daily
Traffic (AADT). A summary of the
traffic data from these existing survey stations is given in the table below:
Table 19.1: Survey Data 1990 - 2000
|
Survey Station, N22 |
AADT |
% HCVs |
Annual Traffic Growth Rates (%) |
|||
|
1990 |
1995 |
2000 |
2000 |
1990-2000 |
1995-2000 |
|
|
West of Ballyvourney |
2,602* |
3,160 |
4,658 |
10 |
7.6 |
8.1 |
|
West of New Cemetery, Macroom |
4,171 |
5,188 |
7,450 |
10 |
6.0 |
7.5 |
|
Coolcour |
5,342 |
7,555+ |
9,560 |
10 |
6.0 |
6.1 |
|
Ovens Bridge |
5,790 |
8,905 |
12,527 |
12 |
8.0 |
7.1 |
|
Poulavone, near Ballincollig |
16,246 |
20,061 |
18,459 |
10 |
# |
# |
* 1992 figures - no data
available for 1990
+ 1996 figures - no data
available for 1995
# AADT too variable to provide growth rate
The observed data can be briefly summarised as follows:
·
AADT flows in 2000
ranged between 4,700 vehicles per day at the western end of the study road to
18,500 vehicles per day at the eastern end.
· The percentage of heavy commercial vehicles (%HCV)
in 2000 was between 10 and 12% of AADT along the study section. For the majority of the survey stations the
%HCV did not change significantly from 1990 to 2000.
· The observed annual traffic growth rates over the
period 1990 to 2000 were generally high (between 6% and 8%).
· The observed annual traffic growth rates over the
most recent period, 1995 to 2000, were also generally high (between 6% and
8%). The National Roads Needs Study
(NRNS) has adopted 1995 as the traffic growth base year. The NRA annual growth rates for the period
1995 - 2000 are 6% for all national primary roads. The NRNS contains slightly higher than national average growth
rates for the N22 between Ballyvourney and Ballincollig.
· Traffic flows at Ballincollig are the highest of
the five sites. The 1990 and 1995 AADT figures for this site represent a
relatively high base. It should be
noted that this location is in fact marginally outside the study area and much
influenced by Ballincollig traffic.
·
AADT’s and %HGV’s are
broadly consistent with flows quoted in RT580 ‘National Roads and Traffic Flow
1999’ for the N22 although the reference locations/sections are not directly
compatible.
A search of existing data sources found no existing traffic count data
for the regional roads within the study area, and no origin/destination or
travel time data.
Traffic surveys were conducted for the study during May and June
2001. The results of these surveys are
summarised in the following section and traffic survey locations are shown on
Fig 19.1.
Classified turning movement surveys at:
·
both N22/R619
junctions;
·
N22/R582 junction.
·
N22/R618 junction
·
N22/R584 junction;
·
N22/R590 junction;
and
·
N22/R585 junction.
Temporary automatic traffic
counts (ATCs) at 17 locations, comprising
the most significant roads, below Regional status, joining the N22 over the
study section. These are listed below
(traffic was counted by direction, northbound and southbound unless otherwise
stated):
·
Site 17: Local Road South of N22, SW of Ballymakeery
(NE/b & SW/b)
·
Site 16: Local Road North of N22, East of
Ballymakeery (NE/b & SW/b)
·
Site 15: Local Road South of Lynch’s Crossroads
·
Site 14: Local Road North of Lynch’s Crossroads
·
Site 13: Local Road South of River Sullane, West of
Macroom
·
Site 12: Local Road North of N22, Macroom
·
Site 11: Local Road South of N22 (S of Macroom)
·
Site 10: Local Road West of N22 (E/b & W/b)
·
Site 9: Athsollis Bridge, South of N22
·
Site 8: Local Road South of N22 (North of
Kilmurry)
·
Site 7: Local Road South Ryecourt Bridge, Farnanes
·
Site 6: Local Road North of N22, Farran
·
Site 5: Local Road South of N22, Farran
·
Site 4: Local Road North of N22, West of Ovens
·
Site 3: Local Road West of Ovens, South of N22
·
Site 2: Local Road Southwest of Ovens Bridge
·
Site 1: Local Road South of N22 (Near Ovens)
The Roadside Interview Surveys collected origin-destination
information at seven locations within the study area, as below:
·
N22 west of
Ballyvourney;
·
N22 near Coolcour;
·
N22 east of Ovens;
·
R582 north of N22;
·
R590 south of N22;
·
R585 south of N22;
and
·
R619 north of N22.
Journey times were surveyed along eight
major routes within the study area. The
routes were as follows:
·
N22 between
Ballyvourney and Ovens;
·
R582 between study
boundary and N22 study boundary.
·
R618 between R619 junction
and N22 junction;
·
R584 between study
boundary and N22 junction;
·
R587 between study
boundary and R584 junction;
·
R590 between study
boundary and N22 junction;
·
R585 between study
boundary and N22 junction; and
·
R619 between R618
junction and N22 junction;
All turning movement surveys were undertaken as
continuous 12 hour (0700 - 1900) full manual classified counts for each
movement from/to each arm of all the junctions selected. The
following vehicle classifications were used (taken from NRA DMRB HD24/96): -
·
Car
·
Light Goods Vehicles
·
OGV1 (2 and 3 axle
rigid)
·
OGV2 (3 axle and more
articulated, 4 axle rigid)
·
Buses and coaches
·
Other
The automatic traffic counts were undertaken for
a minimum of one week to enable reasonable estimates to be made of the average
weekday traffic flows. Counting equipment was checked regularly to ensure
it was functioning correctly and that data collection was continuous.
The ATC data was collected for three main
purposes:
·
to
factor the origin-destination trip data collected at roadside interview sites
to average weekday flow levels;
·
to
calibrate traffic flows in the traffic model along screen-lines and cordon; and
·
to
validate traffic flows in the traffic model.
Roadside Interviews (RSI) were conducted at all
locations in accordance with relevant Republic of Ireland requirements. The
methodology set out in TA 11/81 was used as the basis for the RSI survey. The direction of interview at all sites was
inbound into the study area. Survey
duration was 12 hours (0700-1900) with a simultaneous classified traffic count.
The surveys were carried out with the full co-operation and assistance of the
Co. Cork Garda.
The following information was collected by the
Roadside Interview surveys: -
·
Vehicle
Type (car, van, heavy goods vehicle (rigid), articulated vehicle)
·
Trip
Purpose (commuting, business, retail, personal business, holiday/tourist,
other)
·
Number
of Occupants
·
Origin
and Destination (place name and county). If either origin or destination was in
Macroom, an additional question on the name of the street/area was asked
·
Type
of parking used (for trips with destination in Macroom only)
Journey time surveys employed the floating car
method. A minimum of four runs, both
directions, were completed for each route in each of three time periods;
morning peak (0700 - 0900), afternoon peak (1700 - 1900), and inter peak (1000
- 1600).
A long term ATC will be placed on the N22 in the
immediate future to provide an indication of variations in flow over periods
greater than one week. This will assist
in the derivation of robust estimates of AADT and help to confirm the accuracy
of the traffic work undertaken to date.
This ATC will be maintained for at least the remaining duration of the
study.
The latest complete accident data, covering the period 1996 to 2000,
for the study section of the N22 between Ballyvourney and Ballincollig has been
provided by Cork County Council. This is summarised below:
·
A total of 127 injury
accidents
·
8 were fatalities
(6.3% of total)
·
37 were serious
(29.1% of total)
·
82 were minor injury
(64.5% of total)
·
Personal Injury
Accident Rate of 0.197 per million vehicle kilometres
The personal injury accident rate along the route varies significantly
year by year, as shown in Table 19.2.
Table 19.2: N22 Personal Injury Accident Rate By Year
|
Year |
Personal Injury Accident Rate (PIA Rate) |
|
1996 |
0.302 |
|
1997 |
0.209 |
|
1998 |
0.174 |
|
1999 |
0.135 |
|
2000 |
0.192 |
|
1996 - 2000 |
0.197 |
It can be seen that the average Personal Injury Accident rate for the
route over the period from 1996 to 2000 is similar to the National average of
0.20 to 0.21 per million vehicle kilometres.
However, when the PIA rate is compared year by year it can be seen that
the accident rate along the route varies significantly, with accident rates of
0.302 in 1996 and 0.135 in 1999. The
N22 reported severity split of 6.3%/29.1% is higher than the national average
of 5.4%/28.9% for fatal/serious accidents respectively. In conclusion, the accident data indicates
that the existing section of road has an accident rate comparable to the
national average for a National Primary road, while the severity of accidents
along the route is slightly worse than the national average for a National
Primary Road.
Access to the new N22 Ballyvourney to Ballincollig road will be
limited with infrequent junctions and no minor accesses. This will significantly reduce potential
traffic conflict areas. It is therefore
to be expected that the improved road will constitute a safer travelling
environment than the existing road. The
NRA default rates for the relevant types of new road are as follows:
Table 19.3: Default PIA Rates
|
Road standard |
Personal injury accident rate (PIAs per million vehicle kms) |
|
Dual 2-lane carriageway |
0.12 |
|
Wide single 2-lane carriageway |
0.18 |
|
Single 2-lane carriageway |
0.17 |
These accident rates are all lower than the observed accident rate of
0.197 PIAs per million vehicle kilometres on the existing N22. This indicates the potential for accident
savings following scheme opening, irrespective of the carriageway standard
adopted.
In order to carry out the traffic and economic assessment of the N22
Ballyvourney - Macroom - Ballincollig improvement it is necessary to develop a
calibrated traffic model of the existing road network for the study area. The model can then be utilised to undertake
comparative assessments of the route improvement options.
The traffic model has been developed using the modelling software
SATURN and consists of specific AM peak hour, PM peak hour and Inter-peak hour
models. The traffic model required the
following data: -
·
Traffic counts
·
Origin – destination
data
·
Trip purpose
·
Vehicle type
·
Journey times and
speeds
·
Network carriageway
standards
·
Link lengths
·
Junction
configuration and control
·
Speed limits
The programme of traffic surveys provided the requirements for the
first five of these items. A network
inventory of link lengths based on OSI maps, NRA and county council databases
and route inventory surveys was compiled for the study area. This, in turn,
provided the last four items of data in the above list.
The draft traffic survey report and survey data was completed in July
2001. The table below provides a brief summary of the existing traffic flows in
the study area as revealed by the programme of classified counts undertaken for
the study.
Table 19.4: Summary Of Traffic Flows 2001
|
Road No. |
Location |
Survey Date |
12 hour flow (two-way vehs) |
% HGV |
|
N22 |
Site 27: West of Ballyvourney |
24/5/01 |
5,042 |
9.1 |
|
N22 |
Site 26: East of Macroom |
23/5/01 |
7,150 |
10.4 |
|
N22 |
Site 22: West of R582 |
29/5/01 |
6,599 |
8.4 |
|
N22 |
Site 23: West of R618 |
29/5/01 |
9,109 |
9.4 |
|
N22 |
Site 21: West of R584 |
23/5/01 |
8,056 |
8.9 |
|
N22 |
Site 20: West of R590 |
22/5/01 |
7,196 |
10.1 |
|
N22 |
Site 24: West of R585 |
22/5/01 |
6,453 |
10.7 |
|
N22 |
Site 19: West of R619 (West) |
22/5/01 |
7,298 |
9.8 |
|
N22 |
Site 18: East of R619 (East) |
22/5/01 |
7,121 |
9.1 |
|
N22 |
Site 25: West of Ballincollig |
23/5/01 |
8,612 |
10.4 |
|
R582 |
Site 31: North of Macroom |
24/5/01 |
2,635 |
9.7 |
|
R590 |
Site 30: North of Crookstown |
6/6/01 |
1,908 |
9.7 |
|
R585 |
Site 29: North of Crookstown |
6/6/01 |
1,072 |
13.7 |
|
R619 |
Site 28: North of N22 |
6/6/01 |
139 |
12.2 |
A maximum 12 hour (0700-1900) flow of 9,100 vehicles was recorded
immediately east of Macroom, before the R618 junction. Proportions of HGV’s average around 8-9% on
the N22.
The counts were carried out in May and June, which are regarded as
neutral months and suitable for such surveys in Ireland.
Traffic flows on the regional roads connecting into the N22 are both
significantly lower than on the N22 itself and highly variable between
roads. The R582, for example, carries
2,600 vehicles per 12 hour period while the R619 carries less than 150 over the
same period. This latter is probably an
exceptional case representing a section of very poor horizontal and vertical
alignment.
The completed RSI forms were processed to a common zone plan. A
validation check has been undertaken on the survey data. The total number of
vehicles surveyed at the seven RSI sites during the 12 hour survey period was
measured at 13,734 with a total of 6,780 roadside interviews completed equating
to an overall sample rate of 45.7%. The sample rates at the individual sites
were as follows:
Table 19.5: RSI Sample Rates
|
Site |
12 Hour Count |
Total No. Interviews |
Sample Rate (%) |
|
Site 25: N22 – West of Ballincollig |
4447 |
1189 |
26.7 |
|
Site 26: N22 – East of Macroom |
3619 |
1289 |
35.6 |
|
Site 27: N22 – West of Ballyvourney |
2596 |
1501 |
57.8 |
|
Site 28: R619 – North of N22 |
54 |
41 |
75.9 |
|
Site 29: R585 – North of Crookstown |
558 |
421 |
75.4 |
|
Site 30: R590 – North of Crookstown |
1076 |
776 |
72.1 |
|
Site 31: R582 – North of Macroom |
1384 |
1063 |
76.8 |
|
Total |
13734 |
6280 |
45.7 |
The following table provides the same information for the PM peak hour
(1700-1800), the busiest single hour of the day and consequently the first hour
to be modelled in order to assist in scheme operational assessment.
Table 19.6: RSI Sample Rate (1700-1800)
|
Site |
PM Peak Hour Count |
Total No. Interviews |
Sample Rate (%) |
|
Site 25: N22 – West of Ballincollig |
121 |
523 |
23.1 |
|
Site 26: N22 – East of Macroom |
119 |
314 |
37.9 |
|
Site 27: N22 – West of Ballyvourney |
175 |
271 |
64.6 |
|
Site 28: R619 – North of N22 |
4 |
4 |
100.0 |
|
Site 29: R585 – North of Crookstown |
41 |
47 |
87.2 |
|
Site 30: R590 – North of Crookstown |
114 |
122 |
93.4 |
|
Site 31: R582 – North of Macroom |
74 |
119 |
62.2 |
|
Total |
648 |
1400 |
46.3 |
A summary of the travel time survey data is provided in the table
below. The primary application of this data was in the coding and validation of
do minimum speeds in the traffic model and economic assessment networks.
Table 19.7: Travel Time Survey Data
|
Route No. |
From |
To |
Road |
Distance (km) |
Average Speed (kph) |
||
|
AM Peak |
Inter-Peak |
PM Peak |
|||||
|
1 |
Ovens |
Ballyvourney |
N22 |
40.8 |
61 |
59 |
59 |
|
2 |
Farnanes |
Coachford |
R619 |
9.2 |
50 |
48 |
48 |
|
3 |
Castlemore Br. |
Beal na Blath |
R585 |
5.7 |
65 |
52 |
62 |
|
4 |
Crookstown |
Carrigeen Xrds |
R590 |
5.1 |
51 |
50 |
49 |
|
5 |
Harnett' s Cross |
Inchigeelagh |
R584 |
14.6 |
65 |
61 |
66 |
|
6 |
Toon Br. (R584) |
Kilmichael |
R587 |
8.3 |
86 |
83 |
84 |
|
7 |
Macroom |
Coachford |
R619 |
12.2 |
57 |
57 |
57 |
|
8 |
West Macroom |
Dromree Xrds |
R582 |
3.1 |
55 |
60 |
59 |
Note: Unless stated start
point of route is on N22
These travel time results reveal the lack of variation in travel
speeds over the day with inter-peak speeds comparable to those in the peak
periods. There is also little variation by direction. Likewise, with the exception of route 6 covering the R587 for
which the results are unusually high, there is only a limited range of travel
speeds across the eight routes.
An initial analysis of the data obtained from the automatic traffic
count (ATC) sites has produced an hourly flow profile and the ratios between AM
peak hour, PM peak hour, average Inter-peak hour, 12 hour, 16 hour, 18 hour and
24 hour flows. A summary of this analysis is contained in the table below.
These factors are used in the economic analysis in which the entire day is
modelled rather than individual hours.
Table 19.8: Analysis Of ATC Data
|
Time Period |
Weekday (M-F) Ratio |
Daily (M-Su) Ratio |
|
AM Peak Hour (0800-0900) |
0.079 |
0.066 |
|
PM Peak Hour (1700-1800) |
0.087 |
0.084 |
|
Average Inter-Peak Hour (0900-1700) |
0.058 |
0.060 |
|
12 Hour (0700-1900) |
0.757 |
0.743 |
|
16 Hour (0600-2200) |
0.926 |
0.918 |
|
18 Hour (0600-0000) |
0.978 |
0.971 |
|
24 Hour |
1.000 |
1.000 |
AM peak hour (0800-0900), PM peak hour (1700-1800) and Average
Inter-Peak (0900-1700) hour trip matrices have been developed from the coded
origin/destination survey data. The matrix consists a total of 46 zones. The
zoning system used effectively consists of three tiers, detailed area level in
Macroom, major settlement level in the counties of Cork, Kerry and Killarney,
by county and group of counties beyond this point.
The hourly matrices have been factored to account for the survey
sample rate and converted to passenger car units (pcus) by applying a factor of
1.0 for cars and lgvs and 2.0 for hgvs and buses/coaches. The matrices input to
the SATURN model, for the purposes of validation, are therefore May 2001 hourly
pcu matrices. The hourly pcu format is particularly well suited to the
application of SATURN.
The matrix estimation technique is being used as part of the matrix
development to take account of unsurveyed trips, in particular those using some
of the regional and lesser roads which feed into the N22 but were not included
in the O/D survey cordon. It is rarely possible to cover all such entry/exit
points of a study network particularly where, as with the current study, prior
information is lacking on the traffic volumes using such roads. The matrix
estimation technique is commonly applied in such cases.
The model has been through the validation process in which the output
base year flows are compared with observed traffic flows from manual and
automatic counts. Satisfactory validation is said to have occurred when a
target proportion, 85% in DMRB, of model network links meet specified
convergence criteria. SATURN uses the GEH statistic as its measure of
convergence with values below 5 indicating an acceptable level of convergence.
Full details of the traffic modelling process is provided in the Local
Model Validation Report (LMVR) GD00454/RT/010.
Model traffic growth follows NRA's predictions for National (Primary)
Roads as given in the National Roads Needs Study. These can be summarised as
follows:
Table 19.9: NRA Growth Rates
|
Vehicle Type |
Traffic Growth Rates (% per annum) |
||
|
2000-2010 |
2010-2020 |
2020 beyond |
|
|
Light |
3.75 |
1.40 |
0.46 |
|
Heavy |
2.76 |
1.13 |
0.41 |
The traffic model has been validated against the base year of 2001 and
has been accepted for use by Cork County Council. The model has been used to obtain forecast future traffic flows
for both full scheme opening (2009) and design (2024) years.
The National Roads Authority (NRA) which is responsible for all
National Roads in Ireland has adopted the UK Department of Transport’s
inter-urban and rural road economic assessment program COBA (Cost Benefit Analysis)
version 10 as the standard method of economic evaluation of National Road
schemes.
In brief, COBA compares the benefits of a road project, in the form of
travel time savings, vehicle operating cost savings and accident savings with
the costs, capital and recurrent, of the project. All values are presented in
monetary terms allowing a direct comparison to be made between cost and
benefits. Those costs and or benefits of a scheme which cannot be quantified in
monetary terms, such as social and environmental impacts, have to be assessed
outside COBA.
The default price and discount base year for COBA in Ireland as used
by NRA is 1996.
The economic analysis by COBA modelling was not carried out on every
route option between Nodes 1 and 16.
Due to the large number of these options, individual economic analyses
were limited to alternatives with distinctly different alignments, lengths and
costs. In addition, during early route
assessment, certain routes were identified as unlikely to be the preferred
option. Economic analysis of these
routes was also not carried out.
It was concluded that a further economic analysis would be undertaken
for comparison purposes, if the chosen route were not one of the following improvement
options (for which COBA modelling has been carried out):
· East of Macroom: Green, Red, Blue and Yellow.
Modelled in combination with:
· West of Macroom: Yellow and Green/Link/Yellow
It should also be noted that the Yellow and Blue routes east of Macroom
have each been modelled with both a dual two-lane, and a two-lane wide single
carriageway standard between Macroom and Ballincollig.
Each of these route options have been compared to the Do-minimum
scenario over a 20 year period commencing in 2009, the planned opening year for
the full scheme.
See Chapter 18 for cost estimates.
For the purpose of comparing the proposed route options, construction
of each route is expected to commence in mid 2006 and end in late 2008, with a
10%:40%:50% chronological split between the three years in which construction
occurs. It has been assumed that land
costs are incurred entirely during the first year of construction.
It has also been assumed that preparation and supervision costs will
comprise an additional 13.8% and 5% respectively of the value of the total cost
of each option.
For the Do-Minimum situation, it is assumed that cost will consist
purely of maintenance of the existing road network - see section 19.4.7.
COBA uses two adjustment factors to take account of variations in
prices, the Retail Price Index (RPI) which is a general measure of inflation
and the Relative Price Factor (RPF) which applies to construction costs only
and reflects the short term volatility of the construction industry.
An RPF of 1.0 has been used given that the change in construction
costs in Ireland would appear to have been broadly similar to the general
change in prices over the period 1996 to 2001.
An appropriate RPI value has been input to the COBA modelling to reflect
the 1.14 factor for inflation between 1996 and 2001 (obtained from the Irish
Consumer Price Index) that has been used in the calculation of construction
costs.
The Do Minimum network consists of the existing road network with the
addition of the western end of the Ballincollig bypass.
The geometric characteristics of the network links were obtained from
a series of site visits, while broad parameters such as hilliness and bendiness
were taken from 1:50,000 maps.
The Do Something network differs from the Do Minimum network only in
respect of the inclusion of the appropriate improvement option, each of which
consist of five or six links representing the proposed scheme.
Each improvement scheme has been modelled as a single two-lane
carriageway with a 60 mph limit. In the
cases of the Yellow and Blue routes east of Macroom, the modelling has also
included an alternative standard of dual two-lane carriageway with 70 mph speed
limit between Macroom and Ballincollig.
The location of scheme junctions varies between alternative routes but
the principal junctions are as follows:
·
Existing N22 at
Ballyvourney
·
With the R582 to the
west of Macroom
·
With the Ballyveerane
road to the north of Macroom
·
With the R618 and
R584 to the south-west of Macroom (except Green route)
·
With the R585 and
R590 near Crookstown (Blue and Yellow routes)
·
With the R619 near
Coachford (Green route only) and
·
Existing
N22/Ballincollig bypass at Ballincollig.
The junctions to the north and west of Macroom have been modelled in
COBA as at-grade roundabouts while those to the south and east have been
modelled as grade-separated junctions.
The precise form of grade-separated junction has not been specified and
will be determined at a later stage of the project. It is also possible that
the form and size of particular junctions will be revised subsequently.
For the Do Minimum network, traffic volumes have been produced by the
SATURN traffic model of the N22 current road network. The model and its
development are described in full in the Local Model Validation report. For input to COBA link flows from the SATURN
model have been used. These values are for the 2009 Opening Year AM (0800-0900)
and PM (1700-1800) peak hours and the average inter-peak hour (0900-1700).
These together cover a 10 hour day (0800-1800) which has been factored up,
using a factor derived from the study ATC data, to 12 hour flows for input to
COBA. These flows are summarised for the existing N22 in Table 19.10.
As with the Do Minimum, the output of the traffic model for each of
the modelled time periods was combined to give 12 hour (0700-1900) flows for
input to COBA for the Do Something Situation.
Table 19.10 below details these 12 hour forecasts, as input to COBA, for
each option by section for 2009.
Table 19.10: Opening Year (2009) Traffic Flows On The Existing N22 In
The Do Minimum Situation
|
Link No. |
From |
To |
2009 - 12 hr Traffic |
|
181 |
Ballyvourney |
Ballymakeery |
6,200 |
|
180 |
Ballymakeery |
Ullanes junction |
8,000 |
|
179 |
Ullanes junction |
Rahoonagh junction |
7,700 |
|
178 |
Rahoonagh junction |
Coolnacaheragh |
7,700 |
|
260 |
Coolnacaheragh |
Lissacressig |
7,700 |
|
261 |
Lissacressig |
Carrigaphooca bridge |
7,700 |
|
177 |
Carrigaphooca bridge |
R582 junction |
7,700 |
|
176 |
R582 junction |
Ballyveerane road junction |
12,300 |
|
175 |
Ballyveerane road junction |
The Square, Macroom |
12,500 |
|
174 |
The Square, Macroom |
Church Road junction |
9,300 |
|
173 |
Church Road junction |
Pedestrian crossing, Macroom |
11,000 |
|
172 |
Pedestrian crossing, Macroom |
R618 junction |
11,300 |
|
217 |
R618 junction |
R584 junction |
10,900 |
|
226 |
R584 junction |
Dunisky |
10,000 |
|
227 |
Dunisky |
Athsollis Bridge |
11,400 |
|
228 |
Athsollis Bridge |
Kilmurry junction |
11,000 |
|
146 |
Kilmurry junction |
R590 junction |
10,200 |
|
141 |
R590 junction |
R585 junction |
7,800 |
|
133 |
R585 junction |
Farnanes junction (R619) west |
9,100 |
|
129 |
Farnanes junction (R619) west |
Farnanes junction (R619) east |
8,800 |
|
123 |
Farnanes junction (R619) east |
Currahaly crossroads |
8,800 |
|
116 |
Currahaly crossroads |
Ovens bridge |
8,900 |
|
111 |
Ovens bridge |
Ovens |
7,300 |
|
274 |
Ballincollig bypass west |
|
9,700 |
Table 19.11: 2009 Traffic Flows On The Improved N22 In The Do
Something Situation For Each Improvement Option
|
Route Option |
From |
To |
2009 - 12hr Traffic |
|
West of Macroom: East of Macroom: |
Ballyvourney |
North of Ballymakeery |
6,200 |
|
North of Ballymakeery |
R582 junction |
6,100 |
|
|
R582 junction |
Ballyveerane road junction |
6,900 |
|
|
Ballyveerane road junction |
R584/R618 junction |
6,300 |
|
|
R584/R618 junction |
R590/R585 junction |
10,000 |
|
|
R590/R585 junction |
Ballincollig bypass |
9,100 |
|
|
West of Macroom: East of Macroom: |
Ballyvourney |
North of Ballymakeery |
6,200 |
|
North of Ballymakeery |
R582 junction |
6,900 |
|
|
R582 junction |
Ballyveerane road junction |
6,400 |
|
|
Ballyveerane road junction |
Coachford |
9,200 |
|
|
Coachford |
Ballincollig bypass |
7,600 |
|
|
West of Macroom: East of Macroom: |
Ballyvourney |
North of Ballymakeery |
6,200 |
|
North of Ballymakeery |
R582 junction |
6,100 |
|
|
R582 junction |
Ballyveerane road junction |
5,800 |
|
|
Ballyveerane road junction |
R584/R618 junction |
5,100 |
|
|
R584/R618 junction |
R619 junction |
10,000 |
|
|
R619 junction |
Ballincollig bypass |
7,900 |
|
|
West of Macroom: East of Macroom: |
Ballyvourney |
North of Ballymakeery |
6,300 |
|
North of Ballymakeery |
R582 junction |
6,100 |
|
|
R582 junction |
Ballyveerane road junction |
6,900 |
|
|
Ballyveerane road junction |
R584/R618 junction |
6,300 |
|
|
R584/R618 junction |
R585/R590 junction |
10,000 |
|
|
R585/R590 junction |
Ballincollig bypass |
9,200 |
|
|
West of Macroom: East of Macroom: |
Ballyvourney |
Ballymakeery junction |
6,200 |
|
Ballymakeery junction |
R582 junction |
7,800 |
|
|
R582 junction |
Ballyveerane road junction |
8,000 |
|
|
Ballyveerane road junction |
R584/R618 junction |
7,400 |
|
|
R584/R618 junction |
R590/R585 junction |
10,000 |
|
|
R590/R585 junction |
Ballincollig bypass |
9,100 |
|
|
West of Macroom: East of Macroom: |
Ballyvourney |
Ballymakeery junction |
6,200 |
|
Ballymakeery junction |
R582 junction |
7,800 |
|
|
R582 junction |
Ballyveerane road junction |
6,400 |
|
|
Ballyveerane road junction |
Coachford |
9,400 |
|
|
Coachford |
Ballincollig bypass |
7,600 |
|
|
West of Macroom: East of Macroom: |
Ballyvourney |
Ballymakeery junction |
6,200 |
|
Ballymakeery junction |
R582 junction |
7,800 |
|
|
R582 junction |
Ballyveerane road junction |
6,400 |
|
|
Ballyveerane road junction |
R584/R618 junction |
6,000 |
|
|
R584/R618 junction |
R619 junction |
10,000 |
|
|
R619 junction |
Ballincollig bypass |
7,900 |
|
|
West of Macroom: East of Macroom: |
Ballyvourney |
Ballymakeery junction |
6,200 |
|
Ballymakeery junction |
R582 junction |
7,800 |
|
|
R582 junction |
Ballyveerane road junction |
8,000 |
|
|
Ballyveerane road junction |
R584/R618 junction |
7,400 |
|
|
R584/R618 junction |
R585/R590 junction |
10,000 |
|
|
R585/R590 junction |
Ballincollig bypass |
9,200 |
Flow groups, E-Factor, M-Factor and Seasonality Index are all assumed
to remain unchanged from the Do Minimum situation.
Route Option Cross-sections
The NRNS provides guidance on selection of preferred cross-sections
for a new route. The NRNS recommends
that the route should be designed to provide a “Level of Service” of “D” based
on the projected AADT flows 15 years after the route has opened. The “Level of Service” measurement reflects
operating speeds, freedom to manoeuvre, the response to traffic interruptions,
safety, comfort and convenience of the driver and passengers. The projected traffic flows for the design
year (2024) have been obtained and converted into AADT flows for the purpose of
establishing a preferred cross-section.
Table 19.12 below summarises the projected Annual Average Daily Traffic
(AADT) Flows for the year 2024 for the Do Minimum situation.
Table 19.12 Existing and Design Year Annual Average Daily Traffic
Flows (AADT) - Do Minimum Situation
|
From |
To |
2001 - AADT |
2024 – AADT |
|
Ballyvourney |
Ballymakeery |
6,500 |
12,400 |
|
R582 junction |
Ballyveerane road junction |
12,600 |
18,700 |
|
Ballyveerane road junction |
Macroom centre (east) |
13,400 |
19,100 |
|
R584 junction |
R590 junction |
11,600 |
18,100 |
|
R585 junction |
R619 junction |
9,500 |
14,400 |
|
Currahaly crossroads |
Ovens bridge |
9,200 |
14,100 |
Table 19.12 includes estimates of 2001 AADT flows, which have been
derived from the traffic model. These
AADT estimates for the N22 provide a comparison with those from Cork County
Council's historic (1990-2000) traffic count data on the study section of the
N22, summarised in section 19.1 above.
The two sets of AADT estimates are broadly compatible although it is
apparent that the study survey data gives higher estimates on the western,
Ballyvourney, section and slightly lower estimates at the eastern, Ovens
Bridge, section of the N22.
Table 19.13 shows the projected 2024 AADT flows on the routes.
Table 19.13 Design Year Annual Average Daily Traffic Flows (AADT) for
Route Options
|
Route Option |
From |
To |
2024 – AADT |
|
West of Macroom: East of Macroom: |
N22 - Slievereagh |
East of Ballyvourney |
10,100 |
|
East of Ballyvourney |
R582 |
10,000 |
|
|
R582 |
Ballyveerane |
11,200 |
|
|
Ballyveerane |
R584 |
10,300 |
|
|
R584 |
R590 |
16,400 |
|
|
R590 |
Ovens |
14,800 |
|
|
West of Macroom: East of Macroom: |
N22 - Slievereagh |
East of Ballyvourney |
10,200 |
|
East of Ballyvourney |
R582 |
11,300 |
|
|
R582 |
Ballyveerane |
10,400 |
|
|
Ballyveerane |
Coachford |
15,000 |
|
|
Coachford |
Ovens |
12,500 |
|
|
West of Macroom: East of Macroom: |
N22 - Slievereagh |
East of Ballyvourney |
10,200 |
|
East of Ballyvourney |
R582 |
10,000 |
|
|
R582 |
Ballyveerane |
9,400 |
|
|
Ballyveerane |
R584 |
8,300 |
|
|
R584 |
R619 |
16,300 |
|
|
R619 |
Ovens |
13,000 |
|
|
West of Macroom: East of Macroom: |
N22 - Slievereagh |
East of Ballyvourney |
10,400 |
|
East of Ballyvourney |
R582 |
10,000 |
|
|
R582 |
Ballyveerane |
11,200 |
|
|
Ballyveerane |
R584 |
10,300 |
|
|
R584 |
R590 |
16,400 |
|
|
R590 |
Ovens |
15,000 |
|
|
West of Macroom: East of Macroom: |
N22 - West of Ballyvourney |
East of Ballyvourney |
10,100 |
|
East of Ballyvourney |
N22 – Carrgaphooca |
12,800 |
|
|
N22 – Carrgaphooca |
R582 |
12,800 |
|
|
R582 |
Ballyveerane |
13,100 |
|
|
Ballyveerane |
R584 |
12,100 |
|
|
R584 |
R619 |
16,400 |
|
|
R619 |
Ovens |
14,800 |
|
|
West of Macroom: East of Macroom: |
N22 - West of Ballyvourney |
East of Ballyvourney |
10,200 |
|
East of Ballyvourney |
N22 – Carrgaphooca |
12,800 |
|
|
N22 – Carrgaphooca |
R582 |
12,800 |
|
|
R582 |
Ballyveerane |
10,500 |
|
|
Ballyveerane |
Coachford |
15,300 |
|
|
Coachford |
Ovens |
12,500 |
|
|
West of Macroom: East of Macroom: |
N22 - West of Ballyvourney |
East of Ballyvourney |
10,100 |
|
East of Ballyvourney |
N22 – Carrgaphooca |
12,800 |
|
|
N22 – Carrgaphooca |
R582 |
12,800 |
|
|
R582 |
Ballyveerane |
10,400 |
|
|
Ballyveerane |
R584 |
9,900 |
|
|
R584 |
R619 |
16,300 |
|
|
R619 |
Ovens |
13,000 |
|
|
West of Macroom: East of Macroom: |
N22 - West of Ballyvourney |
East of Ballyvourney |
10,100 |
|
East of Ballyvourney |
N22 – Carrgaphooca |
12,700 |
|
|
N22 – Carrgaphooca |
R582 |
12,800 |
|
|
R582 |
Ballyveerane |
13,100 |
|
|
Ballyveerane |
R584 |
12,100 |
|
|
R584 |
R619 |
16,400 |
|
|
R619 |
Ovens |
15,000 |
The traffic flows in Table 19.13 are taken from the study model for
each of the alternative routes.
For the Do Minimum situation, observed accident data has been input to
COBA to provide a precise calculation of the existing accident rate rather than
using national average rates. Accidents
in the Do Something situation have been modelled as a function of link and
junction types, traffic flows and standard rates and costs. The scheme has been modelled as a modern
single two-lane carriageway road with hard shoulder, with the exception of the
Yellow and Blue routes east of Macroom (between Macroom and Ballincollig) where dual two-lane carriageway has been
modelled in addition to single two-lane carriageway. The appropriate NRA accident rates and costs have been input to
COBA to be applied in the evaluation.
In the absence of the proposed scheme it has been assumed that the
existing road network , together with the Ballincollig bypass, would be
maintained to its current standard.
Maintenance costs have been taken directly from the standard NRA value
for the appropriate road standards and summarised in Table 19.14 below.
Table 19.14: Road Maintenance Costs for Do Minimum Road Network
|
Road Type |
Maintenance Cost (€/km/year) |
|
Single Two-Lane Road |
8,170 |
|
Dual Two-Lane Road |
15,930 |
Source: National Road Needs
Study Technical Report, Chapter 6 "Cost-Benefit Analysis of Interurban
Sections" Table 8 (unpublished). Confirmed by NRA as data to be used in
COBA analysis.
As with the Do Minimum road maintenance costing for the Do Something
Scenario was derived from the standard NRA value for single two-lane rural
roads. The scheme has been assumed to take the per kilometre rate for a single
two-lane carriageway road.
The economic evaluation has not, to date, included an assessment of
delays to traffic during construction.
Consideration will be given to their inclusion, probably through the
application of the UK DETR program QUADRO, at preliminary design stage.
COBA outputs a number of economic performance indicators for the
scheme under evaluation. The two
generally considered most significant are the Net Present Value (NPV) and the
Benefit/Cost Ratio (BCR).
The NPV shows by how much, in monetary terms, the benefits of a scheme
outweigh the costs. A positive NPV shows that the scheme is currently viable, a
negative NPV that it requires amendment or postponement.
The Benefit/Cost Ratio (BCR) allows for the satisfactory comparison of
schemes of differing sizes by using scheme cost as a divisor. A value of
greater than 1.0 indicates the economic viability of the proposed scheme.
The results of the evaluation, including NPV and BCR are shown in
Table 19.15.
Sensitivity tests will be conducted on the Preferred Route when
confirmed. These tests may include the following:
·
30 year evaluation
period
·
Reduced and increased
base year traffic
·
Low and high traffic
growth forecasts
·
Reduced and increased
scheme capital costs
No sensitivity tests have been carried out to date.
The results of the comparative economic evaluation, shown in full in
Table 19.15, can be summarised as follows:
The best economic results are obtained with the Yellow alignment west
of Macroom and the Red alignment east of Macroom. Together, these alignments
give a Net Present Value (NPV) of Euro 41.278m and a Benefit/Cost Ratio (BCR)
of 1.40.
All the alternative alignments evaluated produced positive NPVs with
the exception of the Green-Purple-Yellow/Yellow (single carriageway) with an
NPV of Euro -1.803m and a BCR of 0.984.
The results indicate that for the Blue and Yellow alignments east of
Macroom a dual carriageway scheme is slightly more economically attractive than
a wide single carriageway. However, this increase in standard to dual
carriageway does not result in either Blue or Yellow outperforming the Green or
Red alignments.
This comparison of routes has not included an assessment of a Macroom
bypass in isolation because such an alternative is effectively independent of
the overall scheme alignment and does not, as such, form part of the route
selection process. However, an assessment of the construction of a Macroom
bypass, both as a first stage of the scheme and in isolation, will be carried
out during subsequent analysis.
Table 19.15: Summary Of Economic Evaluation Results, N22 Ballyvourney
- Macroom - Ballincollig Improvement
|
West of Macroom alignment |
GREEN/LINK/YELLOW |
YELLOW |
||||||||||
|
East of Macroom alignment |
GREEN |
RED |
YELLOW |
YELLOW |
BLUE |
BLUE |
GREEN |
RED |
YELLOW |
YELLOW |
BLUE |
BLUE |
|
E X P E N D I T U R E
(€M) |
|
|
|
|
|
|
|
|
|
|
|
|
|
(A) DO-SOMETHING
SCHEME COST |
111.879 |
105.962 |
123.954 |
113.598 |
128.906 |
119.220 |
106.624 |
100.707 |
118.699 |
108.343 |
123.651 |
113.964 |
|
(B) DO-MINIMUM -
SCHEME COST |
|
|
|
|
|
|
|
|
|
|
|
|
|
MAINTENANCE EXPENDITURE SAVING: (C) - TRAFFIC RELATED |
-2.621 |
-2.473 |
-3.965 |
-2.665 |
-3.878 |
-2.621 |
-2.520 |
-2.373 |
-3.865 |
-2.565 |
-3.777 |
-2.520 |
|
(D) - NON
TRAFFIC RELATED |
|
|
|
|
|
|
|
|
|
|
|
|
|
PRESENT VALUE OF COSTS
PVC = A - B - C - D |
114.500 |
108.436 |
127.920 |
116.264 |
132.784 |
121.840 |
109.144 |
103.080 |
122.564 |
110.908 |
127.428 |
116.484 |
|
B E N E F I T S (€M) |
|
|
|
|
|
|
|
|
|
|
|
|
|
(E) TIME - LINK
TRANSIT |
146.488 |
144.097 |
149.355 |
132.856 |
154.136 |
138.426 |
148.992 |
152.262 |
158.872 |
142.372 |
163.767 |
148.057 |
|
(F) TIME -
JUNCTION DELAY |
-16.286 |
-15.389 |
-14.465 |
-14.657 |
-14.352 |
-14.544 |
-16.560 |
-16.112 |
-15.482 |
-15.676 |
-15.361 |
-15.557 |
|
(G) VEHICLE
OPERATING COSTS - LINKS |
-7.447 |
-3.689 |
-20.708 |
-14.111 |
-17.032 |
-10.741 |
-9.326 |
-6.309 |
-22.862 |
-16.263 |
-19.271 |
-12.979 |
|
(H) ACCIDENTS -
LINK AND JUNCTION COMBINED |
13.182 |
13.671 |
22.102 |
10.371 |
22.763 |
11.539 |
13.411 |
14.517 |
23.232 |
11.501 |
23.829 |
12.606 |
|
(J) CHANGES IN
USER COSTS DURING CONSTRUCTION |
|
|
|
|
|
|
|
|
|
|
|
|
|
(K) CHANGES IN
USER COSTS DURING MAINTENANCE |
|
|
|
|
|
|
|
|
|
|
|
|
|
PRESENT VALUE OF BENEFITS PVB = E + F + G + H + J + K |
135.938 |
138.692 |
136.285 |
114.461 |
145.516 |
124.681 |
136.517 |
144.358 |
143.761 |
121.934 |
152.963 |
132.126 |
|
NET PRESENT VALUE NPV = PVB - PVC |
21.438 |
30.257 |
8.365 |
-1.803 |
12.732 |
2.840 |
27.373 |
41.278 |
21.197 |
11.026 |
25.534 |
15.642 |
|
BENEFIT/COST RATIO PVB / PVC |
1.187 |
1.279 |
1.065 |
0.984 |
1.096 |
1.023 |
1.251 |
1.400 |
1.173 |
1.099 |
1.200 |
1.134 |
Notes: Values
in €M in 1996 prices and discounted to 1996.