20    STRUCTURES

20.1  Introduction

This chapter discusses and gives an overview of the structural requirements associated with the various route options presented in the route selection report.

All the route options will require new structures to carry the N22 over various obstacles ranging from streams to rivers, existing roads and the reservoir.  Likewise, all the routes will necessitate new overbridges to carry existing roads and farm access tracks over the new N22.

This report summarises the different structural requirements of the various route options and discusses particular considerations associated with the major crossing over the Carrigadrohid / Inishcarra Reservoir.

20.2  Route Options

20.2.1              Structure Requirements

A summary of the preliminary structure requirements, subject to revision at further design stages, along the different route options is given in Table 20.1.  The table provides details of the numbers of each structure type. A more detailed breakdown of each structure, detailing obstacle crossed, assumed span and width, is provided in Appendix 20. 

Table 20.1 Summary of Structure Requirements

Route

(Node Nos.)

Numbers of Structure Types

Pipe Culvert

Box Culvert

River Bridge

Underbridge

Overbridge

Reservoir Crossing

Green

(1-16)

4

14

5

4

10

1

Yellow

(1-15)

6

10

10

4

12

1

Red

(7-14)

2

4

0

4

8

1

Blue

(7b-15)

2

10

2

2

12

1

L/01

(4-5)

0

1

3

0

0

0

L/03

(9-13)

0

0

0

1

1

1

L/04

(8-10)

1

0

1

2

0

0

L/06

(12-12a)

0

0

0

0

1

0

 

Ovens to Macroom

All route options require the construction of a substantial new reservoir crossing. This structure is discussed in section 20.3.

The green route (Nodes 6-17) carries the N22 to the north of the Lee Valley between Ovens and Macroom. This area is less populated and comprises of rolling hills with some steep valleys. Numerous regional and local roads are crossed along with a number of rivers feeding into the reservoir system. Slightly fewer number of overbridges are required as less accommodation works will be required for property adjacent to the road.

The red route (nodes 7-14) skirts the southern edge of the reservoirs before crossing the Carrigadrohid reservoir near Classes. A higher percentage of over- and underbridges are required over this half-length of the scheme to avoid stopping-off various access roads and local roads. Also the road will rise steeply out of the Bride Valley and then back down again to the Lee Valley and this route is likely to require either significant earthworks or structural retaining measures to enable the road alignment to meet the required design standards. This route is considered to be a more expensive option in term of structures when compared to the others.

Both the blue (nodes 7-15) and yellow (nodes 7-15) routes run along the Bride Valley before passing north to Macroom, with the yellow route following closely the existing N22 alignment whilst the blue route keeps to the north of Mashanaglass. Both routes require a higher number of structures per kilometre due to their alignments passing through the more populated and densely farmed Bride Valley. The structures along the yellow route will generally be more difficult to construct as the scheme is often adjacent to the existing N22 and extensive traffic management will be required. Both routes will require crossings of the River Bride and /or its tributaries and the River Laney, which will need to be designed to minimise impact on the environment. The yellow route also crosses the Sullane River just before it discharges into the reservoir

Links 3 (Nodes 9-13), 4 (Nodes 8-10) and 6 (Nodes 12-12a) present no particular structural difficulties other than the crossing of the existing N22 at Athsollis Bridge. This will require traffic diversions in a confined area in order to allow construction.

Ballyvourney to Macroom

To the west of Macroom, the green route (Nodes 1-6) remains to the north of Sullane River Valley, taking the route up onto the relatively high moorland. The watercourses at this level are generally smaller and greater use of culverts, as opposed to bridges, is anticipated. The use of culverts will have less impact visually on the environment and will be more economic to construct.

The yellow route (Nodes 1-7) follows reasonably closely to the existing N22 alignment and the Sullane River. This lower level alignment means that the watercourses are larger and therefore more river bridges are required. Two skew crossings over the river, close to one another, are needed near Lynch’s Cross Roads. This route has a higher density of structures per kilometre of road over this section when compared to the green however there are no significant difficulties concerning the structures over this length for either route.

20.2.2              Structural Forms

At this stage in the design process, it has been assumed that the river bridges will generally have a span of 15 – 25m, making allowance for all appropriate environmental considerations adjacent to the watercourse. Underbridges will carry the N22 over national, regional or local roads and they will have open-aspect side spans that will minimise their visual impact on the surrounding area. Overbridges will carry regional and/or local roads over the new N22 and these will also have open-aspect side spans. The culverts will be sized in accordance with the environmental requirements. All structures will be designed to be aesthetically pleasing and fit in with their surroundings whilst having a common approach to detail and finish as agreed by the NRA and Cork County Council.

20.3  Reservoir Crossing

20.3.1              Background

The Inishcarra and Carrigadrohid reservoirs were commissioned in 1957 and are owned and operated by the ESB. The primary purpose of the reservoirs is electricity generation, which is produced at the Inishcarra Generating Station situated beneath the Inishcarra Dam.  There is also a water take-off point at Inishcarra that is operated by Cork County Council. The critical reservoir facts and figures are detailed in Table 20.2.

Table 20.2 Reservoir Facts and Figures

 

Inishcarra

Carrigadrohid

Storage Volume (m3)

29.9 Million m3

42 Million m3

ESB Ownership level (m)

48.49

63.74

Crest Level (m)

49.32

64.51

Max. Operating Level (m)

47.29

63.74

Min. Operating Level (m)

42.99

58.29

Normal Operating Range (m)

44.79 – 46.79

59.29 – 61.79

(Note: All levels to Malin Head datum (Pool Beg datum – 2.71m))

 

The reservoirs store water running off a large catchment area extending into the surrounding hills. The flow of water down the Lee Valley is controlled and regulated through the use of sluice gates at Carrigadrohid and a spillway at Inishcarra. The rainfall in the catchment area is monitored on a 24-hour basis through the use of remote rainfall measuring stations. The catchment area is prone to flash flooding which in turn leads to rapid build-ups of water behind the dams. This volume of water is managed between the two reservoirs and the discharge into the River Lee downstream of the dams is co-ordinated to prevent flooding below the dams.

The two reservoirs are crossed by four road bridges, three of which were built at the time of the dams and are owned and maintained by the ESB. The fourth at Carrigadrohid is a pre-reservoir structure. The ESB bridges (Rooves Bridge, Bealahaglashin Bridge and Lee Bridge) are multi-span reinforced concrete structures. The reinforced concrete beam and slab decks are supported by pairs of reinforced concrete piers founded on the reservoir bed. At this stage it is unclear on the foundation type for the structures. The Carrigadrohid bridge appears to be a masonry multi-arch structure.

20.3.2              Constraints Affecting the Proposed Reservoir Crossing

The following site-specific constraints will need to be assessed and considered in the design of the proposed bridge:

·       Wave levels of approx. 300mm

·       Cork County Council – water take-off at Inishcarra and planning issues. Construction must not affect the water quality. All development will need to go through the regulatory planning process. The Lee Valley is identified as an area of Scenic Importance and Recreational Importance and new structures will need to complement and blend in with the existing environment.

·       Caoilte (Forestry Board) – Farran Wood. The section of reservoir adjacent to the wood is to be developed into an international rowing venue.

·       South Western Fisheries Board – Coarse angling. The reservoirs are used extensively by anglers and construction should not disrupt fish stocks and/or the anglers.

·       Cork Power Boat Club – water-skiing on the Dripsey Channel.

·       Carrig Waterski Club – water ski club at Caum upstream of the Carrigadrohid dam.

·       Kayak club

·       Sailing and pleasure craft – the reservoirs are used by dinghies and motorised craft. No boats greater than 6 horsepower are allowed to use the reservoirs. Clearance should be provided that is comparable to that under the existing structures.

·       Reservoir operation – the ESB need to be able to manage the water levels to cope with potential flash floods from October to February. From March to September the ESB are able to raise and lower the water levels to assist construction works.

20.3.3              Route Option Locations

The Reservoir crossings identified by the different route options are summarised in Table 20.3 below.

Table 20.3 Reservoir Crossing Options

Route

Start

End

Length over water (m)

Max Water level

(m)

Max. depth of water at crossing (m)

Chainage

Road Level

Chainage

Road Level

Green

33+480

56.0

33+830

60.0

350

47.29

21.7

Link

(Nodes 9-13)

25+420

66.0

25+560

60.0

140

47.29

10.4

Red

23+090

71.0

23+260

73.0

170

63.74

14.8

Blue

22+500

72.0

22+770

72.0

270

63.74

10.9

Yellow

20+740

72.0

20+940

73.0

200

63.74

6.6

(Note: All levels to Malin Head datum (Pool Beg datum – 2.71m))

Green Route

This option has the longest length of water crossing at 350m. The water depth is also greatest at this location as the route is closest to the Inishcarra dam and the vertical alignment of the route rises significantly from the north to the south. The combination of these two factors means that the carriageway level is up to 12.8m above water level and 34.5m above the lowest reservoir bed level. Construction in such depth of water will be difficult and therefore it is likely that the span will be increased to a maximum in order to position the piers either outside of the reservoir or in shallow depths of water adjacent to the bank. 

Both banks of the reservoir are bounded by open farmland that will enable easy access for construction.

This option is in an exposed location that will have a significant visual impact on the Lee Valley.

The larger span will result in an increased cost of structure.

Yellow Route

The proposed reservoir bridge for this route option is 200m across the water and it lies close to the Bealahaglashin Bridge carrying the existing N22. At this point the reservoir lies within a well-defined natural channel that is wide but fairly shallow at only 6.6m maximum depth.

The proposed structure would follow a similar vertical alignment to the current N22 giving similar vertical clearances between soffit of bridge and water level.

This location is outside any area of scientific interest and reservoir use is already constrained by the two existing bridges at either end of this channel and the shallow depths of water.

This route option presents the NRA and Cork County Council with the best opportunity to deliver a landmark gateway structure that may assist in adding to the identity of the local area and the town of Macroom. The new crossing will have considerably longer spans than those of the existing structures.

The shallow depth of water and easy access to the site will ease construction.

Red Route

This option has a marginally longer length (170m) of crossing than the link option and the maximum depth of water at this location reaches 14.8m.  At this stage it is envisaged that the crossing will have a significant major span in order to keep the pier construction out of the deeper water and minimise any restriction on the use of he reservoir in the vicinity.

The crossing at this point is exposed to view by the communities either side of the water and thus the impact of the bridge will be more significant.

Construction of the proposed bridge in the location is relatively straightforward however construction traffic will disrupt the minor roads nearby.

Blue Route

The length of this option over the water is 270m and is the second longest crossing option. The maximum water depth is 10.9m at this location and the reservoir bed is likely to rise fairly steadily either side of the original river channel. This topography will enable the relatively straightforward construction of piers within the reservoir either within cofferdams or from temporarily backfilled bunds protruding from either side.

This option places no particular constraints on construction other than the need for temporary access roads to enable site works.

The location of the structure means that it is reasonably well hidden from many of the existing viewpoints however it will be in an area of scientific importance.

The longer length of structure will increase the cost of construction of this option.

Link Route (Nodes 9 to 13)

This option produces the shortest length of structure at 140m. At this location, the reservoir passes through a narrow gorge that has quite steep sides on either bank.

The proposed structure will also be constrained by the proximity of the R618 running along the north side of the reservoir. This route will need to be kept operational and it is therefore envisaged that the bridge will span this road in addition to the reservoir.

The steep-sided banks will make construction more difficult however the screened position of the crossing means that the bridge will be well hidden from much of the surrounding area and is therefore less intrusive on the environment.

The shorter length and shorter span will result in a lower cost of structure.

20.4  Construction Issues

The design of the structures, whatever the selected route option, will consider all the constraints appropriate to that particular location.

It is likely that all of the reservoir crossing options, with the exception of possibly the link route, will require piers to be located within the reservoir. A full survey of the submerged topography will be required after selection of the preferred route however various construction techniques such as cofferdams, temporary earth bunds or reduced water levels within the reservoir during foundation construction will enable pier construction to be undertaken.

The preferred construction material for the bridges will be concrete due to the local availability of materials. If however a landmark structure is proposed for the reservoir crossing, a more lightweight construction material, such as steel, may be utilised.

The use of pre-cast or pre-fabricated elements will need to be kept to within current transport and road haulage restrictions. All routes, except for the yellow route require access along narrow local roads and tracks and therefore long beams and structural elements will be difficult to transport to site. The yellow route will allow relatively greater access along the existing N22 for large elements.

All routes involve crossings that are off-line from the existing N22 and therefore provide a clear site. The red route is located close to the Caum Water-ski club and therefore this may partially restrict construction. The Link Route bridge passes close to the shore-hugging R618 scenic drive and so this will involve traffic management during bridge construction.

The blue and yellow routes between Macroom and Ovens require considerably more construction along the line of existing roads. This will produce more disruption to traffic and potentially to the local population adjacent to the works. Consideration of these aspects will result in longer design and construction programmes along with increased associated costs.

20.5  Conclusion

All of the proposed routes result in realistic and viable structural demands. It is considered that all of the structural requirements can be satisfactorily engineered to meet the Client’s requirements.

A key requirement for the structures is that they complement this area of scenic and recreational importance and therefore emphasis must be given to their environmental and aesthetic design. This objective can result, through good design, in a positive enhancement to the locality on some of the routes (yellow and link) and no adverse effect on the remaining routes (green, red and blue).

 

Back to Contents