Description:
Scheme is complete.
The works are located on the N20 National Primary Route between Buttevant and Charleville from Velvetstown to Shinanagh for approximately 2.2km. The type of work involved is the removal of failed sections of pavement, subsequent strengthening of these sections and resurfacing with bituminous macadam. Works will also include site clearance, drainage and utility works, road markings and traffic management.
Status:
Completed
Planned Start Date:
September 2018
Scheduled Date Of Completion:
November 2018
Road Closure:
No
Diversion:
N/A
Temporary Traffic Management:
Yes
Speed Limit Restriction:
N/A
Completed On:
N/A