Description:

Scheme commenced in January 2018 and is now complete.
The works are located on the N25 National Primary Route at Castlemartyr East from the bridge in Castlemartyr Village to a point approximately 2.2km east at Knockane crossroads. The type of work involved is the removal of failed sections of pavement, subsequent strengthening of these sections and resurfacing with bituminous macadam. Works also include storm water drainage, flood containment embankment works, new footpaths and kerbs, installation of new watermain on behalf of Irish Water, undergrounding of overhead services, tree surgery, roadside drainage works, traffic signs and road markings and traffic management.

Status:
Completed
Planned Start Date:
January 2018
Scheduled Date Of Completion:
November 2018
Road Closure:
No
Diversion:
N/A
Temporary Traffic Management:
No
Speed Limit Restriction:
N/A
Completed On:
N/A