Description:
Scheme commenced in April 2018 and is complete
The works are located works are approximately 3km in length and located on the N71 National Secondary Route in and around Leap Village. The type of work involved is the removal of failed sections of pavement, subsequent strengthening of these sections and resurfacing with bituminous macadam. Works will also include site clearance, footpath and paved area repairs, watermain replacement and associated works on behalf of Irish Water, drainage and iron works repair, road markings and traffic management.
Status:
Completed
Planned Start Date:
April 2018
Scheduled Date Of Completion:
November 2018
Road Closure:
No
Diversion:
N/A
Temporary Traffic Management:
Yes
Speed Limit Restriction:
N/A
Completed On:
N/A